Project: Water Rehabilitation Project for Ondo State
Assignment Name
| Country |
|---|
Water Rehabilitation Project for Ondo State | Nigeria | Location within Country
| Professional staff provided by your firm |
|---|
Ondo State | 8 | | Name of Client | Number of Staff |
|---|
Federal Government of Nigeria and Ondo State Water Corporation | 57 | | Address | Number of staff months/Project Duration |
|---|
Alagbaka Housing Estate, PMB 704 Akure, Ondo State | 1254
| | Start Date | Completion Date | Approx. Value of services in Current US$ |
|---|
| Â | Â | $408,119.66 | | Name of Associated Consultants If any | Number of months of professional staff provided by associated consultants |
|---|
Ace Lucas and Partners | 18 | | Name of Senior Staff (Project Director/Coordinator, Team Leader) Involved and Functions Performed: |
|---|
- Project Director/Coordinator: K.G.
- Project Coordinator: John Rowe,
- Project Engineer: Faisal Mirza,
- Project Manager: Mike Whiting
| | Narrative Description of Project |
|---|
Provision of Technical Consulting Services for improvement of water supply system for various towns and cities in Ondo State, Nigeria | | Description of actual services provided by your staff |
|---|
Work included implementation, co-ordination and monitoring of Customer Enumeration and Mapping and a Water Audit/Tariff Study as well as preparation of Operation and Maintenance Manuals. The project included the aerial photography of the Ondo State land area and mapping as well as location of water mains in 4 Towns of Ondo State. |
|